You can synchronize task data between CollabNet
TeamForge and Microsoft Project from
within a Project file.
The
CollabNet
TeamForge Task Manager Add-in
for Microsoft Project adds the
Synchronize with CollabNet
TeamForge
option to your Microsoft Project
File menu.
Important: When you synchronize task data between Microsoft
Project and CollabNet
TeamForge , only certain
fields' data is retained.
You must have the task administration
permission for the
CollabNet
TeamForge project with which you
want to synchronize your Microsoft Project plan.
-
Make sure your Microsoft Internet Explorer proxy settings are
configured correctly to access the Internet, whether or not you are
using Microsoft Internet Explorer as your Web browser.
If you receive a connection error when synchronizing task data, check
with your system administrator for your organization's proxy
settings.
-
Open the Microsoft Project file that you want to synchronize with
CollabNet
TeamForge.
Note: You can also synchronize using a blank Microsoft Project file.
Use this method if you want to do a one-way import from CollabNet
TeamForge to
Microsoft Project.
-
From the File menu, choose .
-
In the Login to CollabNet
TeamForge window,
provide the following information:
- Your CollabNet
TeamForge user name and password.
- The server name of your organization's CollabNet
TeamForge installation.
Note: Do not enter the http:// or
https:// before the server name.
-
Click Login.
-
In the CollabNet
TeamForge Selection
Dialog window, choose the CollabNet
TeamForge project
and task folder with which you want to synchronize your Microsoft
Project plan, and click Next.
-
If your Microsoft Project plan contains any conflicts that
would prevent successful synchronization, a list of
possible problems appears in the Incompatible Tasks
window. Click Cancel, then correct
any issues. Repeat until all synchronization issues are
corrected.
-
If one or more tasks are assigned to resource names that do
not have an exact match in CollabNet
TeamForge , the Resource Assignment window appears. For all tasks
that do not have exact resource matches, you must reassign
the tasks.:
-
Click OK.
The Synchronization Summary window lists the following:
- All the tasks that were added or deleted in CollabNet
TeamForge that will be imported into Microsoft Project.
- All the tasks that were added or deleted in Microsoft
Project that will be exported to CollabNet
TeamForge.
-
Click OK.
- If you do not have any conflicting task changes, your tasks
are now synchronized. To establish the relationship
between your Microsoft Project plan and the CollabNet
TeamForge task folder, save the changes to your Microsoft Project
plan.
Note: If you choose not to save, your
synchronization changes will not be saved in
Microsoft Project and you will not be able to
perform subsequent synchronizations with that task
folder. After you have saved synchronization changes
once, you can then choose not to save your changes
to Microsoft Project. However, your changes are
always saved in CollabNet
TeamForge.
Note: Use this method if you want to do a one-way export
from Microsoft Project to CollabNet
TeamForge.
- If you have conflicting task changes, the Task Conflict
window appears.
You can use all values assigned in
Microsoft Project or use all values assigned in
CollabNet
TeamForge.
Note: When editing start and end dates, you
must choose both values from the same source.
For example, you cannot choose a start date
from CollabNet
TeamForge and an end date from Microsoft
Project.
-
Click Next.
Your tasks are now synchronized, and you can save the changes to your Microsoft
Project plan. For future synchronizations, your Microsoft Project plan is now
bound to the
CollabNet
TeamForge task folder with which
you synchronized. You will not be prompted to select a task folder after the first
synchronization.
Note: If you want to synchronize your Microsoft Project plan with
a different task folder, you must unbind it from
CollabNet
TeamForge. To unbind your
Microsoft Project plan from
CollabNet
TeamForge , click .
After you unbind your Microsoft Project plan, you cannot
synchronize it with the original task folder, but you can synchronize
it with any other task folder.