When you export tasks from Microsoft project to CollabNet TeamForge , if a task is assigned to a resource name that does not have an exact
match in CollabNet TeamForge , you will be provided various options for assigning the task to a resource during synchronization.
Note: When a resource name in Microsoft Project exactly matches a user name in
CollabNet TeamForge user.
The
Resource Assignment window appears during the synchronization process, after you have selected the option in Microsoft Project.
- In the Resource Assignment window for the task, choose whether to assign the task to yourself, or to any project member with
the appropriate permissions, or leave it unassigned.
-
Select whether or not you want to apply the resource mapping to all tasks assigned to that resource.
- Click OK.
The synchronization process continues.